Enhanced B17 Design Capability announced
- Details
Good News – a rare commodity at the moment.
- Details
The B17 SLT engineering team have commenced discussions with potential partners for the various items of the rolling chassis prior to placing orders, while we await Ricardo Rail Ltd. of Derby's approval of the design definition for this next phase and other required documentation.
- Details
With the completion and approval of the static mainframe, the engineering effort is now concentrating on the rolling chassis. The rolling chassis combines the static mainframe and all parts associated with each axle set for each pair of coupled wheels.
- Details
Whilst we wait for the design approval and can start ordering the first components for the rolling chassis (the Hornblocks and Horn Stays) we have started to investigate supplies for components such as the Cab and the Smoke Box. Following our philosophy of using, where possible, local suppliers, we have had preliminary discussions to get indicative cost and to appraise material availability/sizes/form + sections against the LNER drawings, bearing in mind differences between preferred sizes imperial and metric and obsolescence.
- Details
Rolling Chassis Final Design